1.1. Assembly Procedure

Assembly Procedure

Note: Cleanliness is an important factor. Before assembly, all parts should be thoroughly cleaned in cleaning fluid. Allow the parts to air dry. Wiping cloths or rags should not be used to dry parts. Lint may be deposited on the parts which may cause later trouble. Inspect all parts. If any parts are worn or damaged, use new parts for replacement. Dirt and other contaminants can damage the precision components of the pump or of the motor. All disassembly and all assembly procedures must be performed on a clean work surface and in a clean hydraulic area. Keep cleaned parts covered and protected at all times.

Note: Check the O-ring seals for wear or for damage. Replace the O-ring seals, if necessary.



    Illustration 1g00805548

  1. Install the fittings. Install O-ring seal (17) to plug (16).

  2. Install ball (14), valve (15), and plug (16) in block (8).


    Illustration 2g00805547

  3. Install O-ring seals (13) to block (5).


    Illustration 3g00805546

  4. Install O-ring seal (11) to plunger (9). Install spring (12), spool assembly (10), and plunger (9) to block (5).

  5. Repeat Step 4 for the other side of block (5).


    Illustration 4g00805545

    ------ WARNING! ------

    Improper assembly of parts that are spring loaded can cause bodily injury.

    To prevent possible injury, follow the established assembly procedure and wear protective equipment.


  6. Install block (8) to block (5) with bolts (6).

  7. Install bracket (7) with the bolts. Place rubber cover (4) in position.


    Illustration 5g00805544


    Illustration 6g00805543

  8. Install pedal assembly (2) to the implement pilot valve with bolts (3).

  9. Install rubber pedal (1) to the pedal assembly.

End By:

  1. Install the implement pilot valve. Refer to Disassembly and Assembly, "Pilot Valve (Implement) - Install".

Information System:

315C Excavator Machine Systems Pilot Valve (Implement) - Install
315C Excavator Machine Systems Pilot Valve (Implement) - Disassemble
315C Excavator Machine Systems Pilot Valve (Implement) - Remove
315C Excavator Machine Systems Undercarriage Frame - Install
315C Excavator Machine Systems Track Carrier Roller - Install
315C Excavator Machine Systems Shuttle Valve - Install - Straight Travel
315C Excavator Machine Systems Undercarriage Frame - Remove
315C Excavator Machine Systems Shuttle Valve - Remove - Straight Travel
315C Excavator Machine Systems Swing Drive - Install
315C Excavator Machine Systems Swing Drive - Remove
315C Excavator Machine Systems Shuttle Valve - Remove - Auxiliary Control
W345B Series II Material Handler Machine System Specifications Swing Drive - Left Swing Drive and Right Swing Drive
315C Excavator Machine Systems Shuttle Valve - Install - Auxiliary Control
315C Excavator Machine Systems Pilot Valve (Travel) - Remove
315C Excavator Machine Systems Pilot Valve (Travel) - Install
315C Excavator Machine Systems Bucket Linkage Bearings and Seals - Remove
315C Excavator Machine Systems Bucket Linkage Bearings and Seals - Install
315C Excavator Machine Systems Stick Bearings and Seals - Remove
315C Excavator Machine Systems Stick Bearings and Seals - Install
320C, 322C and 325C Excavators Tool Control System Implement Electronic Control Module (Tool)
5130B Excavator Hydraulic Oil Tank Filters - Replace
5230B Excavator Hydraulic System Piston Pump (Implement)
H140CS and H160CS Hydraulic Hammers Hydraulic Hammer Troubleshooting
5230B Excavator Hydraulic System Piston Pump (Swing)