315C Excavator Machine Systems Shuttle Valve - Install - Straight Travel Caterpillar


Shuttle Valve - Install - Straight Travel
`
1.1. Installation Procedure

Installation Procedure

Note: Cleanliness is an important factor. Before installation, ensure that all parts and mating surfaces are clean. Inspect all parts. If any parts are worn or damaged, use new parts for replacement.

Note: Check the O-ring seals for wear and for damage. Replace the O-ring seals, if necessary.




    Illustration 1g00636154

    Typical example

  1. Install shuttle valve (4) beneath the cab floor. Install bolts (5) and the washers in the shuttle valve.



    Illustration 2g01021556

  1. Connect all hose assemblies (3) to shuttle valve (4) .

  1. Fill the hydraulic system. Refer to Operation and Maintenance Manual, "Hydraulic System Oil Level - Check" and Operation and Maintenance Manual, "Capacities (Refill)".

  1. Start the machine. Check for any leaks. Repair any leaks.



    Illustration 3g00636152

    Typical example

  1. Install plate assembly (2) beneath the cab. Install bolts (1) and the washers in the plate assembly beneath the cab.

  1. Install high efficiency filters in place of the pilot filter, the filter for the case drain, and the return filter.

    Note: High efficiency filters should not be run for more than 250 hours before you change back to the standard filters.

  1. Obtain a hydraulic oil sample from the main S·O·S port. Refer to Operation and Maintenance Manual, "Sampling Interval and Location of Sampling Valve" for the location of the sampling valve.

  1. If the S·O·S sample exceeds ISO 18/15, flush the hydraulic system. Refer to Contamination Control Guideline, SEBF8447.

Information System:

315C Excavator Machine Systems Undercarriage Frame - Remove
315C Excavator Machine Systems Shuttle Valve - Remove - Straight Travel
315C Excavator Machine Systems Swing Drive - Install
315C Excavator Machine Systems Swing Drive - Remove
315C Excavator Machine Systems Shuttle Valve - Remove - Auxiliary Control
W345B Series II Material Handler Machine System Specifications Swing Drive - Left Swing Drive and Right Swing Drive
315C Excavator Machine Systems Pump Control - Install
345B Excavator Equipment Lowering with Engine Stopped
315C Excavator Machine Systems Pump Control - Remove
315C Excavator Machine Systems Main Control Valve - Install
5130B Excavator Fuses - Replace
5130B Excavator Fuel Tank Water and Sediment - Drain
315C Excavator Machine Systems Track Carrier Roller - Install
315C Excavator Machine Systems Undercarriage Frame - Install
315C Excavator Machine Systems Pilot Valve (Implement) - Remove
315C Excavator Machine Systems Pilot Valve (Implement) - Disassemble
315C Excavator Machine Systems Pilot Valve (Implement) - Install
315C Excavator Machine Systems Pilot Valve (Implement) - Assemble
315C Excavator Machine Systems Shuttle Valve - Install - Auxiliary Control
315C Excavator Machine Systems Pilot Valve (Travel) - Remove
315C Excavator Machine Systems Pilot Valve (Travel) - Install
315C Excavator Machine Systems Bucket Linkage Bearings and Seals - Remove
315C Excavator Machine Systems Bucket Linkage Bearings and Seals - Install
315C Excavator Machine Systems Stick Bearings and Seals - Remove