320D2 GC Excavator Machine Systems Stick Bearings and Seals - Remove and Install Caterpillar


Stick Bearings and Seals - Remove and Install
`
1.1. Removal Procedure
2.1. Installation Procedure

Removal Procedure

Table 1
Required Tools 
Tool  Part Number  Part Description  Qty 
9U-5338  Bearing Puller Adapter(1) 
9U-5336 Bearing Puller Adapter(2) 
4C-9634 Puller Stud 
9U-6832 Nut 
6V-3175 Double Acting Cylinder 
3S-6224 Electric Hydraulic Pump (115 Volt)(3) 
9U-5266 Receiving Sleeve 
(1) Used for removing the bearing that is located on the boom side of the stick
(2) Used for removing the bearing that is located on the bucket side of the stick
(3) 8S-8033 Electric Hydraulic Pump (230 Volt) is available.

Start By:

  1. Remove the stick.

Note: For the removal of the sleeve bearings from the stick at the pin joint for the bucket control linkage, refer to Disassembly and Assembly, "Bucket Linkage Bearings and Seals - Remove".



    Illustration 1g00592359

  1. Remove lip seal (1).


    Illustration 2g00592391

  2. Use Tooling (A) to remove the sleeve bearing.

  3. Repeat Steps 1 and 2 in order to remove the lip seal and the sleeve bearing from the opposite side of the stick.


    Illustration 3g00604131

  4. Remove lip seal (2) from the bore for the stick to bucket pin.


    Illustration 4g01302540

  5. Use Tooling (A) to remove the sleeve bearing.

  6. Repeat Steps 4 and 5 in order to remove the lip seal and the sleeve bearing from the opposite side of the stick.

Installation Procedure

Table 2
Required Tools 
Tool  Part Number  Part Description  Qty 
5P-0960  Molybdenum Grease 
1P-0520  Driver Gp 

Note: Make sure that the bearing bores for the sleeve bearings are free of paint and grease prior to the installation of the sleeve bearings.

  1. Lower the temperature of the new sleeve bearing for the heel end of the stick.

  2. Insert the new sleeve bearing into the stick at the connection of the stick and the heel.


    Illustration 5g01032927
    (D) 9.50 ± 0.8 mm (0.374 ± 0.032 inch)

  3. Use Tooling (C) to drive the new sleeve bearing into the bearing bore in the stick. Drive the new sleeve bearing into the bearing bore to the depth of Dimension (D).


    Illustration 6g01032914

  4. Use Tooling (C) to install lip seal (1) in the outside of the sleeve bearing. Install lip seal (1) so that the lip faces outward. Drive the seal until the seal makes contact with the sleeve bearing. Apply Tooling (B) to the sealing lip of lip seal (1) and to the sleeve bearings.

  5. Repeat Step 1 through Step 4 for installation of the sleeve bearing and of the lip seal on the other side of the stick.

  6. Lower the temperature of the new sleeve bearing for the boom end of the stick.

  7. Insert the new sleeve bearing into the stick at the connection of the stick and of the boom.


    Illustration 7g01304546
    (E) 9.5 ± 0.8 mm (0.37 ± 0.03 inch)

  8. Use Tooling (C) to drive the new sleeve bearing into the bearing bore in the stick. Drive the new sleeve bearing into the bearing bore to the depth of Dimension (E).


    Illustration 8g01219099

  9. Use Tooling (C) to install lip seal (3) in the outside of the sleeve bearing. Install lip seal (3) so that the lip faces outward. Drive the lip seal until the lip seal makes contact with the sleeve bearing. Apply Tooling (B) to the sealing lip of lip seal (3) and to the sleeve bearing.

  10. Repeat Step 6 through Step 9 for installation of the sleeve bearing and of the lip seal on the other side of the stick.

End By:

  1. Install the stick.

Information System:

Procedure to Install a Bluetooth Module 481-7118 Wiring Kit on F2 Series Backhoe Loaders {1408}
Installation of the 418-7814 Auxiliary Hydraulic Lines Gp (Boom) on Certain Hydraulic Excavators {5057}
312F and 313F Excavator Machine Systems Electronic Control (Blade System)
320D2 GC Excavator Machine Systems Stick - Remove and Install
320D2 GC Excavator Machine Systems Stick Cylinder - Remove and Install
320D2 GC Excavator Machine Systems Load Control Valve (Stick Cylinder) - Assemble
312F and 313F Excavator Machine Systems Electronic Control (Bucket System)
320D2 GC Excavator Machine Systems Load Control Valve (Stick Cylinder) - Disassemble
320D2 GC Excavator Machine Systems Load Control Valve (Stick Cylinder) - Remove and Install
312F and 313F Excavator Machine Systems Electronic Control (Stick System)
320D2 GC Excavator Machine Systems Bucket Cylinder - Remove and Install
312F and 313F Excavator Machine Systems Shovel Crane - Test and Adjust
320D2 GC Excavator Machine Systems Load Control Valve (Boom Cylinder) - Remove and Install
320D2 GC Excavator Machine Systems Load Control Valve (Boom Cylinder) - Disassemble
320D2 GC Excavator Machine Systems Load Control Valve (Boom Cylinder) - Assemble
320D2 GC Excavator Machine Systems Boom Cylinder - Remove and Install
312F and 313F Excavator Machine Systems Electronic Control (Swing System)
Inspection Procedure for Boom Cylinder Assembly Cracks on Certain 330B, 330C, 345B, 345C, and 345D Excavators {5456, 7562}
312F and 313F Excavator Machine Systems Relief Valve (Swing)
312F and 313F Excavator Machine Systems Oil Makeup (Swing System)
325F Excavator Machine Systems Cab - Remove and Install
312F and 313F Excavator Machine Systems Relief Valve (Cushion Crossover) - Anti-Reaction Valve
316F Excavator Machine System Specifications Pump Head (Main)
318F Excavator Machine Systems Swing Drive