320D2 GC Excavator Machine Systems Bucket Linkage Bearings and Seals - Remove and Install Caterpillar


Bucket Linkage Bearings and Seals - Remove and Install
`
320D2 GC Excavator Machine Systems [M0066452]
IMPLEMENTS
LINKAGE GP
320D2 GC Excavator Machine Systems Bucket Linkage - Remove and Install
320D2 GC Excavator Machine Systems Bucket Linkage Bearings and Seals - Remove and Install
1.1. Removal Procedure
2.1. Installation Procedure

Removal Procedure

Table 1
Required Tools 
Tool  Part Number  Part Description  Qty 
3S-6224  Electric Hydraulic Pump (115 Volt)(1) 
6V-3175 Double Acting Cylinder 
4C-9634 Puller Stud 
9U-6832 Nut 
5P-8625 Receiving Sleeve 
9U-5339 Bearing Puller Adapter 
3S-6224  Electric Hydraulic Pump (115 Volt)(1) 
6V-3175 Double Acting Cylinder 
4C-9634 Puller Stud 
9U-6832 Nut 
4K-0684 Hard Washer 
5P-8625 Receiving Sleeve 
9U-5336 Bearing Puller Adapter 
(1) 8S-8033 Electric Hydraulic Pump (230 Volt) is available.

Start By:

  1. Remove the bucket control linkage. Refer to Disassembly and Assembly, "Bucket Linkage - Remove".


    Illustration 1g00698265

  1. Remove lip seals (1) from the power link (2).


    Illustration 2g01213106

  2. Attach an suitable lifting device to Tooling (A), as shown.

  3. Use Tooling (A) to remove sleeve bearing (3) from the open end of the power link.

  4. Use Tooling (A) to remove the sleeve bearing from the opposite side of the power link.

  5. Remove the sleeve bearings from the closed end of the power link by using Tooling (A).


    Illustration 3g00698407

  6. Remove lip seals (4) from the bore for the idler link in the stick.


    Illustration 4g00698417

  7. Attach an suitable lifting device to Tooling (B), as shown.

  8. Use Tooling (B) to remove the sleeve bearing from the stick.

  9. Use Tooling (B) to remove the sleeve bearing from the opposite side of the stick.

Installation Procedure

Table 2
Required Tools 
Tool  Part Number  Part Description  Qty 
1P-0520  Driver Gp 
5P-0960  Molybdenum Grease 

Note: Refer to Specifications in order to identify the bucket families.

  1. Make sure that the bores in the power link and the bore in the stick are thoroughly clean and free of dirt and debris prior to the installation of the sleeve bearings.

    Note: Make sure that the bearings are installed in the bore so that the identification numbers of the bearings are facing outward.



    Illustration 5g00698602

  2. Lower the temperature of sleeve bearings (5) that will be installed in the closed end of power link (2) to −40 °C (−40 °F).

  3. Use Tooling (C) to install sleeve bearings (5) in the closed end of power link (2). Install the sleeve bearings until Dimension (X) is achieved. Dimension (X) should equal 9.50 ± 0.20 mm (0.374 ± 0.008 inch).


    Illustration 6g00698673

  4. Lower the temperature of sleeve bearings (3) that will be installed in the open end of power link (2) to −40 °C (−40 °F).

  5. Use Tooling (C) to install two sleeve bearings (3) in the open end of power link (2). Install the sleeve bearings until Dimension (Y) is achieved. Dimension (Y) should equal 13.60 ± 0.30 mm (0.535 ± 0.012 inch).


    Illustration 7g00698265

  6. Use Tooling (C) to install lip seals (1) in power link (2). Install the lip seals with the sealing lip toward the outside of the bore. Install the lip seals below the outside surface of the power link.


    Illustration 8g00698695


    Illustration 9g00698698
    View A-A

  7. Lower the temperature of two sleeve bearings (6) that will be installed in the stick to −40 °C (−40 °F).

  8. Use Tooling (C) to install sleeve bearings (6) in the stick. Install the sleeve bearings until Dimension (Z) is achieved. Dimension (Z) must be 9.50 ± 0.80 mm (0.374 ± 0.032 inch).


    Illustration 10g00698407

  9. Install lip seals (4) in the stick. Install the lip seals with the sealing lip toward the outside of the bore. Install the lip seals below the outside surface of the stick.

  10. Apply a thin coat of Tooling (D) to all sleeve bearings.

  11. Apply a thin coat of Tooling (D) to the sealing lip of all lip seals.

End By:

  1. Install the bucket control linkage. Refer to Disassembly and Assembly, "Bucket Linkage - Install".

Information System:

314D CR Hydraulic Excavator Machine Systems Recoil Spring - Assemble
320D2 GC Excavator Machine Systems Bucket Linkage - Remove and Install
C2.4 Tier 4 Final Engines for Caterpillar Built Machines Electronic Unit Injector - Remove and Install
320D2 GC Excavator Machine Systems Bucket - Remove and Install
320D2 GC Excavator Machine Systems Duo-Cone Conventional Seals - Install
320D2 GC Excavator Machine System Specifications Swing Gear and Bearing
307E2 Mini Hydraulic Excavator Machine Systems Hydraulic Lockout Control - Remove and Install
349D2 MHPU Mobile Hydraulic Power Unit Hydraulic System Return Hydraulic System
320D2 GC Excavator Machine System Specifications Upper Frame
C2.4 Tier 4 Final Engines for Caterpillar Built Machines Fuel Manifold (Rail) - Remove and Install
320D2 GC Excavator Machine System Specifications Muffler
316F Excavator Machine System Specifications Air Conditioner Lines
C2.4 Tier 4 Final Engines for Caterpillar Built Machines Turbocharger - Remove and Install
C2.4 Tier 4 Final Engines for Caterpillar Built Machines Engine Oil Cooler - Remove and Install
C2.4 Tier 4 Final Engines for Caterpillar Built Machines Engine Oil Pump - Remove and Install
C2.4 Tier 4 Final Engines for Caterpillar Built Machines Flywheel - Remove and Install
C2.4 Tier 4 Final Engines for Caterpillar Built Machines Cylinder Head - Remove and Install
C2.4 Tier 4 Final Engines for Caterpillar Built Machines Glow Plugs - Remove and Install
312F and 313F Excavator Machine Systems Electronic Control (Pilot System)
312F and 313F Excavator Machine Systems Electronic Control (Main Pump System)
318F Excavator Machine Systems Stick - 2.25 m (7.381 ft)
312F and 313F Excavator Machine System Specifications Fuel Tank
312F and 313F Excavator Machine System Specifications Swing Gear and Bearing
318F Excavator Machine Systems Stick - 3.1 m (10.17 ft)